| Timeline It usually takes from five to seven months to get your store up and running. This depends on how easily you can get financed, find a great location, and complete construction on your space. If you are self-financed and find a location requiring minimal construction, your start-up project should be faster. The timeline below shows the scope of the process. |
| Signed Franchise Agreement: |
Day 1 |
|
|
Site Selection |
60 Days | |
| Business Planning: |
28 Days | |
| Financing: | 45 Days | |
| Site Design and Construction: |
75 Days | |
| Training: | 15 Days | |
| Open to Buy - Intial Inventory: |
60 Days | |
| Grand Opening Weekend: |
3-4 Days |